All 6 units of Fukushima Daiichi Nuclear Power Station have been shut down.
Unit 1(Shut down)
- Reactor has been shut down. However, the unit is under inspection due
to the explosive sound and white smoke that was confirmed after the big
quake occurred at 3:36PM.
- Also, we have been injecting sea water into the reactor core and then
boric acid which absorbs neutron. However, we tentatively ceased the
operation factoring in the impact of potential tsunami following the
earthquake which occurred at 10:15PM.
We are trying to kill the runaway reactor but conflicting proceedures now have us hiding from a potential tsunami and we let the reactor just cook away because we don't know what to do first, second or third.
Unit 2(Shut down)
- Reactor and Reactor Core Isolation Cooling System have been shut down.
Current reactor water level is lower than normal level, but the water
level is steady. After fully securing safety, we are preparing to
implement a measure to reduce the pressure of the reactor containment
vessels under the instruction of the national government.
The damn thing is overheating and producing hydrogen gas. We are going to release hydrogen and radioactivity into the environment. We just hope the hydrogen doesn't blow up again like on Reactor #1. Sorry, our bad.
source,
http://www.tepco.co.jp/en/press/corp...1031234-e.html